MindMap Gallery PMP-Project Integrated Management Review
PMP project integration management chapter knowledge point compilation, pre-examination review, predictive project, integration management is the responsibility of the project manager, the responsibility of integration management cannot be delegated or transferred; the project manager is required to intervene and start the project as early as possible, such as conducting business case and benefits manage.
Edited at 2023-05-20 00:13:56El cáncer de pulmón es un tumor maligno que se origina en la mucosa bronquial o las glándulas de los pulmones. Es uno de los tumores malignos con mayor morbilidad y mortalidad y mayor amenaza para la salud y la vida humana.
La diabetes es una enfermedad crónica con hiperglucemia como signo principal. Es causada principalmente por una disminución en la secreción de insulina causada por una disfunción de las células de los islotes pancreáticos, o porque el cuerpo es insensible a la acción de la insulina (es decir, resistencia a la insulina), o ambas cosas. la glucosa en la sangre es ineficaz para ser utilizada y almacenada.
El sistema digestivo es uno de los nueve sistemas principales del cuerpo humano y es el principal responsable de la ingesta, digestión, absorción y excreción de los alimentos. Consta de dos partes principales: el tracto digestivo y las glándulas digestivas.
El cáncer de pulmón es un tumor maligno que se origina en la mucosa bronquial o las glándulas de los pulmones. Es uno de los tumores malignos con mayor morbilidad y mortalidad y mayor amenaza para la salud y la vida humana.
La diabetes es una enfermedad crónica con hiperglucemia como signo principal. Es causada principalmente por una disminución en la secreción de insulina causada por una disfunción de las células de los islotes pancreáticos, o porque el cuerpo es insensible a la acción de la insulina (es decir, resistencia a la insulina), o ambas cosas. la glucosa en la sangre es ineficaz para ser utilizada y almacenada.
El sistema digestivo es uno de los nueve sistemas principales del cuerpo humano y es el principal responsable de la ingesta, digestión, absorción y excreción de los alimentos. Consta de dos partes principales: el tracto digestivo y las glándulas digestivas.
PMP-Project Integrated Management Review
premise concept
For predictive projects, integration management is the responsibility of the project manager, and the responsibility for integration management cannot be delegated or transferred.
Project managers are required to get involved early in initiating projects, such as conducting business cases and benefits management
Develop project charter
Main points
A document that formally approves a project and authorizes the project manager to use organizational resources in project activities
The project manager should be identified and appointed as early as possible, preferably when the project charter is developed, but at the latest before planning begins
The project charter may be prepared by the sponsor, or by the project manager in collaboration with the sponsoring agency. The project manager should be involved in the development of the project charter to better understand the project
Confirm that the project meets the needs of the organization's strategy and daily operations by preparing a project charter
enter
Business documents (regular review)
Business case (whether it’s worth the investment)
business needs
Cost-benefit analysis
Benefit management plan (when and how to benefit)
Include tangible or intangible benefits
Consistent with company strategy
agreement (contract)
Business environment factors, organizational process assets
Tools and Techniques
expert judgment
Brainstorming
focus group
Those with the same function and field, such as SME (Subject Matter Expert)
guide
Facilitated workshops for cross-functional departments to lead to consensus
Conference management
Have a clear agenda before the meeting; stay on topic during the meeting and handle meeting conflicts; write meeting minutes after the meeting
output
Project Charter
1. Project goals, objectives, success criteria and exit criteria
2. High-level needs, overall budget, overall milestone plan, overall risks, list of key stakeholders, etc.
3. Information about the sponsor and project manager
Hypothetical log
Document all assumptions and constraints throughout the project life cycle
Assumptions
Factors that do not require verification and can be considered correct, true or certain
Constraints
Constraints that affect the execution of a project or process
Develop project management plan
Main points
The process of integrating and binding into a comprehensive project management plan
Plans need to be progressively detailed through ongoing updates, and these updates need to be controlled and approved
enter
Subplans and baselines output from other planning processes
Project Charter
Tools and Techniques
Check List
guide
Meeting: kick-off meeting is the last thing to do in the planning stage
Communicate project goals
Gain team commitment to the project
Clarify the roles and responsibilities of each stakeholder and obtain unanimous buy-in from key stakeholders
output
project management plan
10 major sub-management plans, change management plans, and configuration management plans
3 benchmarks
Performance measurement baseline, project life cycle description, development methodology
Direct and manage project work
Main points
Execute the work identified in the project management plan
The process of implementing approved changes
enter
project management plan
Approved change request
Tools and Techniques
PMIS system
Schedule planning software tools
work authorization system
configuration management system
Information collection and release system
output
Deliverables
verifiable
job performance data
Raw observations and measurements
Problem log
Update issue log
Solving old problems and emerging new ones
Entire project life cycle
Three elements of problem log
question
Responsible
Resolution deadline
change request
Preventive measures against risks
Corrective measures to correct deviations
Defect remediation and quality improvement
Update the general improvement plan (or baseline)
Managing project knowledge
Main points
Use existing knowledge and generate new knowledge to achieve project goals and help organize the learning process
explicit knowledge
Knowledge that is easy to codify using words, pictures and numbers
tacit knowledge
Individual knowledge and knowledge that is difficult to articulate, such as beliefs, experiences, insights, “know-how”
The most important part is to create an atmosphere of mutual trust and encourage people to share knowledge or pay attention to other people's knowledge.
Existing in the minds of individual experts or in social groups and situations, often shared through interpersonal communication and interaction
enter
Lessons Learned Register
Tools and Techniques
knowledge management
tacit knowledge
information management
explicit knowledge
output
Lessons Learned Register
Record and update the entire process
beneficial for future projects
Monitor project work
Main points
Integrate work performance information into work performance reports to let stakeholders understand the current and future status of the project
enter
job performance information
cost forecast
progress forecast
Tools and Techniques
Alternatives Analysis
Choose the best combination of actions to implement, or the best option
Cost-benefit analysis
Determine the most cost-saving measures
Root Cause Analysis
Identify the root cause of the problem, address it at the source, and prevent it from happening again
Earned value analysis
Comprehensive analysis of scope, schedule and cost performance
Deviation analysis
Review differences between target performance and actual performance
trend analysis
Predict future performance based on past results and propose necessary preventive measures
output
job performance report
change request
Implement holistic change control
Main points
Throughout the project, the project manager has ultimate responsibility
Can be made by anyone, can be made orally, but all change requests must be documented in writing
Designate a responsible person in the project management plan or organizational procedures to approve, defer or reject changes (default submitted to CCB)
Changes do not need to be formally controlled by the Implementation Integrated Change Control process until the baseline is established. Once the project baseline is established, change requests must be processed through this process.
Understand the reasons for changes and prevent unnecessary changes. Follow the process: 1. Record 2. Evaluate 3. Submit (project manager submits to CCB) 4. Update 5. Notify
enter
change request
project management plan
Tools and Techniques
change control tools
output
Approved change request
Project file updates
Update changelog
End project or phase
Main points
Normal ending
1. Obtain acceptance
2. Hand over final results
3. Summarize experiences and lessons learned
4. Update organizational process assets
5. Archive
6. Release resources
Project terminated early
1. Investigate and document the cause
2. Handover of completed and unfinished final results
3. Summarize experiences and lessons learned
4. Update organizational process assets
5. Archive
6. Release resources
1. Releasing resources is the last step in closing. If the closing has been completely completed: If a problem or defect occurs, the project manager only needs to coordinate the operation department's intervention in a timely manner. If customers need new features, they can suggest opening a new project. 2. If the finishing touches have not been completely completed: When problems or defects are encountered, the project manager must actively deal with them, and may even need to go through the change process. When encountering new features, you generally have to go through the change process. 3. If closing the current project and starting a new project occur at the same time, give priority to closing the current project.
enter
Project Charter
Deliverables for acceptance
organizational process assets
Project or phase closure guidelines or requirements
Contracts, business documents, etc.
Tools and Techniques
Meeting
output
Handover of final product, service or result
final report
Summarize project performance
organizational process assets
Project or phase closure documents
Before project establishment
New syllabus process areas Task 14 - Specify project governance structure
Determine the appropriate governance structure for the project Define the path and threshold for reporting issues
New syllabus business environment field Task 2 - Evaluate and deliver project benefits and value
Survey benefits identified Document relevant knowledge so benefits can be realized over time Confirm whether to establish a measurement system for benefit tracking Evaluate delivery options to demonstrate value Assess stakeholder value capture progress
Project in progress
Task 9 Integrate project planning activities
Identify key information needs Collect and analyze data to make informed project decisions Analyze aggregated data Integrate project or phase plans Evaluate post-merge plan dependencies
Task 10 Manage project changes
Determine a strategy for handling change Anticipate and accept the need for change (e.g. follow change management practices) Execute change management strategy according to methodology Determine response to changes
Task 16 Ensure knowledge transfer and keep projects ongoing
Discuss responsibilities within the team Outline expectations for the work environment Identify methods for knowledge transfer and exchange
Task 17 Plan and manage project closure and handover
Criteria for project validation and closure Confirm handover preparations Carry out closing activities to close the project or phase