MindMap Gallery PMP
PMP mind map, the contents of project risk management include: reviewing test points, planning risk management, identifying risks, implementing qualitative risk analysis, implementing quantitative risk analysis, planning risk response, implementing risk response, and supervising risk. Let's take a look at it together.
Edited at 2023-05-03 00:12:09El cáncer de pulmón es un tumor maligno que se origina en la mucosa bronquial o las glándulas de los pulmones. Es uno de los tumores malignos con mayor morbilidad y mortalidad y mayor amenaza para la salud y la vida humana.
La diabetes es una enfermedad crónica con hiperglucemia como signo principal. Es causada principalmente por una disminución en la secreción de insulina causada por una disfunción de las células de los islotes pancreáticos, o porque el cuerpo es insensible a la acción de la insulina (es decir, resistencia a la insulina), o ambas cosas. la glucosa en la sangre es ineficaz para ser utilizada y almacenada.
El sistema digestivo es uno de los nueve sistemas principales del cuerpo humano y es el principal responsable de la ingesta, digestión, absorción y excreción de los alimentos. Consta de dos partes principales: el tracto digestivo y las glándulas digestivas.
El cáncer de pulmón es un tumor maligno que se origina en la mucosa bronquial o las glándulas de los pulmones. Es uno de los tumores malignos con mayor morbilidad y mortalidad y mayor amenaza para la salud y la vida humana.
La diabetes es una enfermedad crónica con hiperglucemia como signo principal. Es causada principalmente por una disminución en la secreción de insulina causada por una disfunción de las células de los islotes pancreáticos, o porque el cuerpo es insensible a la acción de la insulina (es decir, resistencia a la insulina), o ambas cosas. la glucosa en la sangre es ineficaz para ser utilizada y almacenada.
El sistema digestivo es uno de los nueve sistemas principales del cuerpo humano y es el principal responsable de la ingesta, digestión, absorción y excreción de los alimentos. Consta de dos partes principales: el tracto digestivo y las glándulas digestivas.
PMP
project risk management
Overview of test points
risk threshold
The risk threshold reflects the risk appetite of the organization and project stakeholders. degree, which is the acceptable degree of variation in project goals
project resilience
Address unexpected risks by strengthening project resilience
Integrated risk management
Certain risks identified at a higher level will be delegated to the project team to manage; Some risks identified at lower levels may be handed over to higher levels for management (if management is most effective outside the project)
planning risk management
Concept test points
Development time
Early completion of the project, later in the project life cycle, may It is necessary to redo this process
enter
Project Charter
project management plan
project files
business environment factors
organizational process assets
Tools & Techniques
expert judgment
data analysis
Stakeholder analysis
Meeting
output
risk management plan
risk management strategy
methodology
Roles and Responsibilities
funds
Schedule
Risk category
Related party risk appetite
measurable risk threshold
Risk probability and impact definition
Based on the risk allocation preferences and thresholds of the organization and relevant parties
Probability influence matrix
report format
track
Identify risks
Concept test points
All project stakeholders should be encouraged to participate
Identifying risks is an iterative process
enter
project management plan
Six major management plans: demand, schedule, cost, quality, resources, and risk
Scope, schedule, cost 3 benchmarks
8Project files
Hypothetical log
Cost Estimate
duration estimate
Use intervals to understand whether estimates are adequate
Problem log
Lessons Learned Register
Similar risks
requirements document
Those requirements are at risk
Resource requirements
Interval to understand whether the estimate is sufficient
Interested Party Register
Participant Responsible Person
protocol
External procurement project resources
Procurement documents
External procurement project resources
business environment factors
organizational process assets
Tools & Techniques
expert judgment
data collection
Checklist
Reference historical information and knowledge base
Interview
data analysis
Root Cause Analysis
Discover the underlying causes of problems and develop preventive measures Shi
Assumptions and constraints analysis
SWOT analysis
File analysis
Interpersonal and team skills
guide
Tip list
Risk categories at the bottom of the risk breakdown structure can be used as a checklist to identify individual project risks Assist the project team in developing ideas
Brainstorming
Meeting
risk seminar
Brainstorming
output
risk register
Conduct qualitative risk analysis, plan risk responses, implement processes such as implementing risk response and monitoring risks, and the results of these processes are also recorded in the risk register
include
Risk name
risk category
Current risk status
one or more reasons
The impact of one or more objectives on the target
Risk trigger conditions
Affected WBS components
time information
When risks are identified
when might it happen
When may it no longer be relevant
and deadlines for action
risk report
Project file updates
Hypothetical log
Problem log
Lessons Learned Register
Conduct qualitative risk analysis
Concept test points
Evaluate the probability and impact of individual project risks and other characteristics to prioritize risks The process of prioritizing and thereby providing a basis for subsequent analysis or action.
This process identifies owners for each risk who are responsible for planning the risk response and ensuring that the response is implemented
enter
project management plan
risk management plan
project files
Hypothetical log
subtopic
risk register
Interested Party Register
Find the person responsible for risk
business environment factors
organizational process assets
Tools & Techniques
expert judgment
data collection
Interview
data analysis
Risk data quality assessment
Understand the evaluation of various aspects of data quality by project stakeholders, including data integrity, objectivity, relevance and timeliness, and then conduct a comprehensive assessment of the quality of risk data
Risk probability impact assessment
Risks with low probability and impact will be placed on a watch list in the risk register for future monitoring
Assessment of other risk parameters
Interpersonal and team skills
guide
Risk classification
Data performance
Probability and Impact Matrix
priority
hierarchy diagram
If more than two parameters are used to classify risks, the "matrix" cannot be used.
Meeting
risk seminar
Review identified risks
Assess probability and impact
Classify and prioritize risks
risk owner
Assign risk owners to individual project risks one by one
Risk owners are responsible for planning risk responses and reporting on the progress of risk management work
output
Project file updates
Hypothetical log
Problem log
risk register
risk report
Conduct quantitative risk analysis
Concept test points
Quantify overall project risk exposure
Not required for every project
Suitable for large or complex projects
Projects of strategic importance
Projects that require quantitative analysis under contract
enter
project management plan
risk management plan
Three major benchmarks: scope, schedule, and cost
project files
Hypothetical log
Estimate basis
Cost Estimate
cost forecast
duration estimate
Milestone List
Major events determine schedule goals and quantitative schedule risks Compare the results of the analysis
Resource requirements
insurance register
risk report
progress forecast
business environment factors
organizational process assets
Tools & Techniques
expert judgment
data collection
Interview
Interpersonal and team skills
guide
How uncertainty manifests
Probability distributions may take many forms, the most commonly used are triangular distribution, normal distribution, lognormal distribution, beta distribution, uniform distribution or discrete distribution
data analysis
simulation
Monte Carlo analysis
Sensitivity Analysis (Tornado Plot)
Determine which individual project risks or other sources of uncertainty have the greatest impact on project outcomes large potential impact.
Decision tree analysis
expected monetary value
influence diagram
output
Project file updates
risk report
uAssessment results of overall project risk exposure
Results of detailed probabilistic analysis of u project
uSingle project risk priority list
uTrends in quantitative risk analysis results
uRisk response suggestions
Plan risk responses
Concept test points
Develop appropriate approaches to address overall project risks and individual project risks; this process will also allocate resources and add related activities to the project documents and project management plan as needed
enter
project management plan
uRisk management plan
Roles and Responsibilities, Risk Thresholds
uResource Management Plan
Coordinate response resources
ucost basis
emergency fund
project files
uLessons Learned Register
uProject schedule
uThe project team dispatches work orders
uResource Calendar
risk register
Low-priority threats and opportunities may simply need to be listed in the watch list portion of the risk register, or contingency reserves may need to be added instead of proactive management measures.
risk report
Interested Party Register
business environment factors
organizational process assets
Tools & Techniques
expert judgment
data collection
Interview
Interpersonal and team skills
guide
Threat response strategy
Report
Not within project scope
Exceeding project manager authority
avoid
may include elimination Reason for threat
Extend schedule
Change project strategy
narrow down
transfer
purchase insurance
Use a performance bond
Guarantee of use
Warranty of use
alleviate
Run more tests with a simpler process
Choose a more reliable seller
Prototype development
Add redundant components
accept
low priority threats
Take the initiative to accept
Establish a contingency reserve to set aside time, money or resources to respond to emergencies
Sheet accepted
Review threats regularly to ensure they have not changed significantly
Opportunity coping strategies
Report
open up
Reduce completion time by allocating the organization's most capable resources to projects
Adopt new technologies or technology upgrades to save project costs and shorten project duration
share
improve
accept
emergency response strategies
Overall project risk response strategy
data analysis
uAnalysis of alternatives
uCost-benefit analysis
decision making
Multi-criteria decision analysis
output
change request
progress baseline
cost basis
Project Management Plan Update
Five major management plans: schedule, cost, quality, resources, and procurement; three major benchmarks: scope, schedule, and cost.
Project file updates
uHypothesis log
uCost forecast
uLessons Learned Register
uProject schedule
uThe project team dispatches work orders
risk register
Agreed coping strategies
Specific actions required to implement selected response strategies
Trigger conditions, signs and early warning signals for risk occurrence
Budget and schedule activities required to implement the selected response strategy
contingency plan, and the risk triggers required to activate the plan
Bounce back planning, used when a risk occurs and primary response measures are insufficient
Residual risks that remain after predetermined response measures have been taken, and risks that are intentionally accepted
Secondary risks directly caused by the implementation of risk response measures
Insurance report
Implement risk responses
Concept test points
Ensure agreed-upon risk responses are executed as planned to manage overall project risk exposure, minimize individual project threats, and maximize individual project opportunities
enter
project management plan
risk management plan
project files
uLessons Learned Register
uRisk Register
The risk register records the agreed risk responses for each individual risk, as well as the Designated responsible person
uRisk Report
Risk reporting includes an assessment of current overall project risk exposure, as well as agreed risks Response strategies also describe important individual project risks and their response plans.
organizational process assets
Tools & Techniques
expert judgment
Interpersonal and team skills
Influence
Project Management Information System (PMIS)
output
change request
After risk responses are implemented, cost baselines and schedule bases may be
Project file updates
uProblem log
uLessons Learned Register
uThe project team dispatches work orders
uRisk Register
uRisk Report
Oversight risk
Concept test points
supervise
Track identified risks
Identify and analyze new risks
Assess the effectiveness of risk management
Implementation of agreed risk response plans
To ensure that the project team and key stakeholders understand the current level of risk exposure, project work should be continuously monitored through the Monitoring Risk process to identify emerging, changing, and obsolete individual project risks.
enter
project management plan
risk management plan
project files
Problem log
Lessons Learned Register
risk register
risk report
job performance data
job performance report
Tools & Techniques
data analysis
Technical performance analysis
Technical performance measures may include: weight, processing time, number of defects, storage capacity, etc.
Reserve analysis
Reserve analysis refers to comparing the remaining contingency reserve with the remaining amount of risk to determine whether remaining reserves are still reasonable
audit
The project manager is responsible for ensuring that risk audits are conducted at the frequency specified in the project risk management plan
Risk audits can be conducted during daily project review meetings
Meeting
risk review meeting
to check and record the wind The effectiveness of the risk response in addressing overall project risks and identified individual project risks
New individual project risks identified
Reassess current risks
Close obsolete risks,
Discuss issues raised by risks
output
job performance information
change request
Recommended corrective and preventive actions
Project Management Plan Update
Any changes to the project management plan are raised as change requests and processed through the organization's change control process. Any component of the project management plan may be affected by this process
project files
Hypothetical log
Problem log
risk register
risk report
Organizational process asset updates
theme
theme