MindMap Gallery project cost management
The PMP project cost management knowledge review includes four parts: planning cost management, estimating costs, formulating budgets, and controlling costs.
Edited at 2022-11-16 03:20:38Microbiologie médicale, infections bactériennes et immunité résume et organise les points de connaissances pour aider les apprenants à comprendre et à se souvenir. Étudiez plus efficacement !
Medical Microbiology Bacterial Infection and Immunity summarizes and organizes knowledge points to help learners understand and remember. Study more efficiently!
The kinetic theory of gases reveals the microscopic nature of macroscopic thermal phenomena and laws of gases by finding the relationship between macroscopic quantities and microscopic quantities. From the perspective of molecular motion, statistical methods are used to study the macroscopic properties and change patterns of thermal motion of gas molecules.
Microbiologie médicale, infections bactériennes et immunité résume et organise les points de connaissances pour aider les apprenants à comprendre et à se souvenir. Étudiez plus efficacement !
Medical Microbiology Bacterial Infection and Immunity summarizes and organizes knowledge points to help learners understand and remember. Study more efficiently!
The kinetic theory of gases reveals the microscopic nature of macroscopic thermal phenomena and laws of gases by finding the relationship between macroscopic quantities and microscopic quantities. From the perspective of molecular motion, statistical methods are used to study the macroscopic properties and change patterns of thermal motion of gas molecules.
project cost management
planning cost management
The concept of several groups of costs
Fixed costs and variable costs
direct costs and indirect costs
Direct costs: can be tracked economically within a project, usually the cost of resources dedicated to a project
Indirect costs: Costs of resources that cannot be tracked economically within a project and are typically shared between several projects or projects and functional operations
Opportunity cost, marginal cost and sunk cost
Marginal cost: refers to the increase in total cost brought by each unit of newly produced products (or purchased products)
Sunk costs: refers to expenses that occurred in the past but are irrecoverable and have nothing to do with current decisions (objectively)
Opportunity cost: refers to the maximum value of something that has to be given up in order to obtain something else. (In the face of the analysis of opportunity costs, companies are required to choose the correct business projects in their operations. The basis is that the actual benefits must be greater than the opportunity costs, so that limited resources can be optimally allocated)
cost management plan
Estimate cost
TT
Bottom-up estimation
three point estimate
parameter estimation
analogy estimation
expert judgment
…
Similar to schedule estimation
O
cost
Estimate basis
cost estimate level
Rough magnitude estimate of ROM (floating range 100%, -25%~75%)
Budget estimate (floating range 35%, -10%~25%)
Certainty estimate (floating range 15%, -5%~10%)
Budgeting
I: Project documents (estimation basis, cost estimate, etc.)
TT: Cost Summary
O
cost basis
Project funding requirements
Project funding is usually invested in increments
Control costs
Earned value analysis triple value
Plan value PV
Earned value EV
Used to judge progress
Actual cost AC
EV is on the left Find PV for progress and AC for cost. Subtract the deviation and divide the exponent.
Determination of project status
The bigger the EV, the better
SV, CV>0, SPI, CPI>1, schedule ahead of schedule, cost balance (good!)
SV, CV<0, SPI, CPI<1, behind schedule, cost overrun (not good!)
How to analyze and respond
SV>0, CV>0, (over schedule, budget balance) well done, keep up the good work;
SV>0, CV<0, (over schedule, budget overrun) too much effort, arrange the work reasonably;
SV<0, CV>0, (schedule behind schedule, budget surplus) spend the cost to grab the progress and rush the work;
SV<0, CV<0, (schedule behind schedule, budget overrun) the project has a problem and needs to be analyzed and changed to solve;
trend analysis
Budget at Completion (BAC): The total budget for performing the work
Estimated to Complete (ETC): The estimated cost to complete the remaining work
Estimate at Completion (EAC): The total expected cost to complete all work, equal to the actual cost to date plus the remaining budget for completion
deviation
Atypical deviation (accidental)
ETC calculation: ETC1=BAC-EV
EAC1=AC ETC1=AC (BAC-EV)
Typical deviation (long term)
ETC calculation: ETC2=ETC1/CPI
EAC2=BAC/CPI